|
Alternatives

This
study will develop and evaluate possible alternatives which appear
to solve the identified problems and to identify possible technical,
environmental and fundability issues.
-
Consideration
will be given to a limited range of alternative actions for the
purpose of identifying viable improvements and eliminating
solutions which are not feasible.
These alternatives shall include, but not be limited to,
consideration of providing additional capacity at existing
crossings, a new crossing, modifying and improving traffic
processing through technology, and other options as relevant.
Approach road/operational alternatives are also needed.
-
Life cycle
costs to maintain both the north and south channel bridges at
the Thousand Islands will be estimated.
The
engineering criteria and an environmental assessment of each of the
alternatives identified for further study shall be developed.
This assessment shall address both U.S. and Canadian
requirements.
-
Concept
level geometric and
service characteristics of each alternative and required
approaches will be developed.
-
Concept
level plans and
profiles for potential location alternatives will be developed,
including approach options.
-
A
general assessment of each feasible alternative’s
impacts on social, economic and environmental considerations
will be made to determine the environmental feasibility of each
of the alternatives.
The
estimated costs, user benefits and suggested funding mechanism for
each alternative identified for continued study will be developed.
-
Highway
user costs for each remaining alternative will be estimated.
-
Possible
right-of-way, construction, operational and maintenance issues
for each feasible alternative
will be identified. Ballpark
construction of toll facilities, customs and immigration
facilities and approach routes will be included in the
development of the planning level cost estimates.
-
The
importance of these international crossings to the local,
regional and national economies shall be documented and the
impact excessive delays can have on international trade and
economic performance will be identified.
The major issues
involved in undertaking each of the alternatives will be addressed.
-
Possible
actions required to implement each of the alternatives such as
those required by federal (U.S. and Canadian), State and
Provincial legislation, Corps of Engineers, SEQRA, NEPA, etc.
will be identified.
-
A
schedule for implementing study recommendations will be
developed.
|